A kitchen remodel goes wrong in the sequencing more often than in the craftsmanship. Cabinets ordered after demolition, counters templated before the cabinets are level, tile set before the electrician has moved the outlets — every one of those costs a week. Here is the order we run in the Valley, and why.

1. Design and selections — before anything is touched

Layout, cabinet line, countertop material, tile, fixtures, appliances and lighting are all chosen and priced before demolition. Cabinets have the longest lead time (four to ten weeks), so the order date sets the demo date, not the other way round.

2. Permits

If plumbing, gas, electrical or structure changes, the project is permitted — through LADBS in the City of Los Angeles, or the city’s own department in Burbank, Glendale, Calabasas and Beverly Hills. Plan check runs in parallel with the cabinet lead time. More on permits here.

3. Demolition and protection

Dust barriers, floor protection, a temporary kitchen set up elsewhere in the house, then the old kitchen comes out. One to three days.

4. Structural and framing

If a wall is coming out, the beam goes in now, with the framing inspection before anything covers it. New window or door openings happen at this stage too. See wall removal.

5. Rough plumbing, gas and electrical

Everything that lives inside the walls and under the floor — new circuits, island power, relocated drains (slab cutting in most Valley houses), gas to the range. Rough inspection follows.

6. Drywall, texture and paint

Walls closed, patched and primed. Painting the ceiling and walls now, before cabinets, saves cutting in around them later.

7. Flooring (usually)

Most floors go in before cabinets so the cabinets sit on the finished floor and appliances can slide out later. The exception is some tile layouts where the cabinets go first — we decide this in design.

8. Cabinets

Set level and plumb, scribed to the walls. Two to four days for a typical kitchen. See custom cabinets.

9. Countertop template and install

The fabricator templates after the cabinets are set; slabs arrive seven to fourteen days later. Sinks are set with the counter. Countertops explained.

10. Backsplash, finish plumbing and electrical, appliances

Tile goes on after the counter is in so the bottom row sits on it. Then faucets, disposal, dishwasher, outlets, switches, lights and the range. Backsplash details.

11. Final inspection and punch list

The inspector signs off; we walk the kitchen with you and fix the list. Then the kitchen is yours.